next steps

We are now running a period of consultation for two weeks until Friday 24th July 2020, so that residents and others can have their say on the plans.

Once the consultation period has ended, we will analyse the feedback received from residents, councillors and others. Once this feedback has been taken on board, we will finalise the plans and submit them to Cornwall Council.

We hope that the plans will be determined at some point before the autumn, and we would hope to begin working on-site in Spring 2021.

The building of the homes would take approximately 4 years and we would continue to communicate with the local community during the construction of the site.

  • Early July 2020

    Pre- Application Public Consultation

  • Late Summer 2020

    Submit Proposals to Cornwall Council

  • Autumn 2020

    Expected Determination of Proposals

  • Spring 2021

    Start on site

  • Winter 2021

    First homes are completed and first residents move in