next steps

We have now analyse the feedback received from residents, councillors and others, taken on board any issues raised, finalised the plans and submitted them to Cornwall Council.

We hope the plans will be determined at some point over the autumn and hope to begin working on site in early 2020.

The building of the homes would take approximately 18 months and we plan to communicate with the local community during the construction of the site.

  • June 2019

    Public Consultation

  • July 2019

    Review feedback and finalise plans

  • September 2019

    Submit plans to Cornwall Council, depending on any issues raised in consultation

  • September - November 2019

    Formal Consultation on proposals

  • December 2019

    Estimated determination

  • Early 2020

    Construction begins on site

  • Mid 2021

    Homes are completed and residents move in